Plan Tasks Execution

Tasks in each change stage are executed sequentially in the order they are organized.

 

To alter the task execution sequence,

  1. Go to the Tasks sub-tab in a change stage.
  2. Click Organize on the task list view.
  3. In the Organize Tasks pop-up, click to move the tasks.
  4. Click Save.
  5. Confirm the order by clicking OK.

 

 

Trigger Tasks

You can trigger tasks in a change stage individually or as a group based on your requirements.

  1. Go to the Tasks sub-tab in a change stage.
  2. Select tasks to trigger.
  3. Click Trigger on the toolbar.

 

 

If you have already marked a group or owner for the task, the triggered task will be assigned to them immediately. Triggered tasks will set the current time as scheduled start time.